Re-Energise Clearance Certificate For HT Equipment
[To be filled by Operation-In-Charge of working area]
Equipment
Unit
Dat Date
Tag No.
Requirement: Emergency Ordinary All Locks & Tags removed
Equipment Earthing Found Intact
All Clearances Returned with Job Completion Certificates
All tools, equipments, manpower and unused materials have been
removed and surrounding area of the said equipment has been cleaned.
Kindly energise the above equipment.
Date : Name :
Time : Designation : (Signature)
JOB COMPLETION CERTIFICATE
[To be filled by Authorised Person of Electrical Operation]
The equipment is energised after performing following Checks / Activities:
YES NO N/A
1. Damaged internals of Breaker / MCC rectified
2. Temporary safety ground/s removed
3. IR Value of Cable / Equipment Checked-found O.K.
4. Back lid / cover of Breaker boxed up
5. All LOTO of isolating device removed
6. Control fuse put back in place
7. Power fuse put back in place
8. Breaker control plug put back on its base
9. Breaker checked in test position & found O.K.
10. Trip circuit found healthy