(1) The following particulars shall be submitted to the Employer's Representative for
his consent not more than seven (7) days after the date of commencement of the
Works
(a) drawings showing the formation works and the layout within the Site of the
Employer and . Employer's Representative's accommodation, the
Contractor's offices, project signboards, principal access and other major
facilities required early in the Contract,together with all service utilities;
(b) drawings showing the layout and the construction details of the Employer
and Employer's Representative accommodation; and
(c) drawings showing the details to be included on the Project signboards.