2.12.4 Insulation
2.12.4.1 Where Service Agreement includes provision of insulation Services, Contractor shall ensure that only properly trained personnel (Contractor or sub-contractor) remove, fabricate and install insulation materials.
2.12.4.2 Provision of insulation materials shall be based on the following:
(1) After disassembly of insulation ,the Contractor shall inform to the Company representative for the damage insulation material .Company representative will inspect materials to determine whether they can be re-used or not.
(2) Insulation material to be replaced with new material shall be approved by Company representative prior installation.
(3) The cost of insulation damage beyond to poor quality of work - insulation material handling , shall be at the Contractor’s own account
(4) All insulation materials shall be stored in a safe place and packed in plastic bags.
(5) All rejected materials shall be packed properly and sent to the waste disposal area. Metal shall be separated from insulation materials.