I have received the Bq for block F Beachfront and it needs to be reviewed before I send to you
I will meet with them at 2pm tomorrow and go through it then issue to you basically once in order we will issue to 3 contractors along with all other tender documents when we get them back I'll do a tender analysis then we can meet and go though it to agree the next step
What normally happens is we will pick 2 out of the 3 and ask them to re submit with a contractors discount to give us there best price. We will also inform them what we will supply regarding materials as well as our nominated sub cons i.e. PSD Windows