Minute of meeting
7/2/57 @site Lopburi
1. Sharp present New Organization Chart.
2. Present process of health and safety policy.
3. Process of security work.
4. Present Schedule Plan Level 3 for the owner approves but in the schedule has only timeline no actual.
5. Master Schedule (Microsoft Project) will send within next week after Schedule Plan Level 3 has approved.
6. K. Phatdanai showed sample activities of CON’s parties on Master schedule in each of state.
7. K. Charin asks for civil work’s detail of this month from K.Yongyuth for send to the owner, K. Yongyuth will send within meeting day.
8. K. Yongyut inform in the meeting about office building work will start on 20-30 March 2014 for the owner find auspicious time for the main post.
9. CM (Ensol) ask for Procedure testing Material form EPC.
10. EPE will set up the Mockup of PV System for Owner testing at in front of site office.
11. In case of build Fence ITD would follow the coordinates specified in the plan, if there are complaints about the area. The EPC will cease operations in such areas before and to continue the other areas of project which no complaints.
12. Mr. Yongyuth proposed about the progress of construction work since start until February 6, 2014
13. The project owner has the right to ask for inspection worked done.