Please be request to prepare the project of Installation hopper for dumpling GMS from dumpling floor to AMF tank for RECO1
The design may be look like the seeding lactose prepare of SCM mixing RECO4 (1st design)
We need to install at Reco1.
This project aim to prevent the safety issue are:
- The carry the GMS to dump at manhole of AMF tank by stair.
- Muscle inflammation of operator.
- Raw material damage if has accident.
Please contact me or K. Lomsak for more information. Thank you for your support.
Pongsomboon, V. (Veerayar)
Processing Manager
FrieslandCampina Thailand
Mobile Phone : 66 817 007 891
89/2 Moo 8 Soi Wat Suansom, Poochaosamingprai Road, Samrongtai Phrapradaeng
Bangkok 10130