Dear Khun Wit,
Based on the photos. Such this heavily down pour and heavies flooded. Nothing we can do much. For the Banchak solar power plant. They must take care for their portion.
As for the 300 rai area. We shall prepare construction drainage water channeling to the temporary water pond.
Therefore, we shall excavate and dig more water pond at the permanent water pond area krub. (See attached photo)
Please discuss with Sup.L and SY Khun Porn krub.
Take note that I will be tighten up with HPD Crystallizer plant meeting in Bangkok office from today till 23rd Jun. and 24th Jun meeting with Paint manufacturer as well.
Therefore, I will not be available for this few days for site visit and meeting. Kindly follow up and update me krub.