3. Technical issues such as inability to deal with large
file sizes and various security issues had to be
overcome. Printing of drawings at site was not
straight forward as it was reported that backgrounds
had to be assembled and some layers were
lost in the file transfer.
4. Although the system worked well with the
principal members of the team, some subcontractors
found it difficult to match the technology.