Production,
To add in , I suggest you need to clear it ASAP for the reject piece as I need the inspection report that we submit to Baker for re inspection their product has defect not more than 2 %. As the reject from QC is too high and this will destroy trust & reputation if we submit the actual report to them. and to prevent too many question and doubt from QA/QC Chevron team to asking once they see the color rejection in each particular item in our facility and sure they will make a report from our rejection.
Please manage anyway to don’t let they found our high rate internal rejection on this X-nipple and Flow coupling. It is good to have the internal NCR but this is the product that we send out. It is terrible if they know the truth.
Please put this for priority kub. This is very critical.