Project B
For project B, the risks identified were categorised into four groups, namely, Risk Project (RP), Risk Design (RD), Risk Manufacture (RM) and Risk Installation (RI), as shown in Table 3. Before the application of any treatment plans, two project risks, RP-003 and RM-006, were rated as Extreme, while the remaining risks were rated as High (see Table 3).