Please check price and date for Lifting test of Electrical load back with TOM.
Below for work plan
1. Electrical load bank to TJ heater is 6 July 2016.
2. Lifting test is 8-15 July 2016.
3. Testing plan at Numsang (Lampchabang) is 18 July 2016. *If shall be postpone to 13-15 July if Lifting test is finish before 12 July 2016.
4. Delivery to SKL is 20-22 July 2016.