In the first case, the production cost per backpack is $40. The second case incurs an additional
holding cost of $.50 per backpack per month. In the third case, an additional penalty cost
of $2.00 per backpack is incurred for each month delay. Boralis wishes to determine the optimal
production schedule for the four months.