Please find the updated project below ;
The FID for this project will be most likely postponed by 1 year.
Original plan
- award EPCI and issue LOA : Sept2015
- EPC prepare detail engineering and bid long lead item : 6 months after receiving LOA (Mar 2016- issue PO for long lead item)
- FID : Jan2016
The new plan( to be reconfirmed)
- FID : Jan2017
- award EPCI and issue LOA : Sept 2015- maintain
- EPC prepare detail engineering and bid long lead item : 12 months after receiving LOA by reducing number of man hours, Sept 2016 - engineering and bid for long lead should be ready but cannot issue PO till Jan2017 when the FID would be approved.
The concept is still the same pass-through, Which Chevron involve in selecting the vendor they feel fit for purpose.
The new FID is to be reconfirmed, it is most likely but not confirm.
We will double check and update you.