See contract, proposal and layout for last line from China.
Delivery can be Feb 28, if they can verbally agree by 1st Dec, contract signed by Dec 4, and deposit latest 15Dec.
Any delays and delivery time will be pushed one week for each week delays.
The price as we know for this line is very low considering the added components and change of specification, I hope the customer will remember this.
I have request from our electrical designer in Europe for the Windak built machines, our standard components for Relays and contactors are Phoenix and Schneider (Telemechanique), very common brands. I don’t think this should be an issue since you can always replace them with similar device from other supplier. Can you please confirm with customer that using Phoenix and Schneider (Telemechanique) is ok?