Dear Rob,
Further to our discussion tonight, I want to summarize my understanding:-
Please be informed as MMTH & MME have not come to see our production at ARKR tomorrow naka.
However, K. Jaroon & His Top management requested to meeting with Aeroklas Management instead which you can see agenda as below :
1. Aeroklas internal policy & alternative solution toward MMTH & MME current situation. (Capacity not enough , Part shortage and Back order)
2. Backup plan to solve this critical situation such as run production line both day & night shift, produce part 7 days a week and etc.
So, please kindly check K. Ekawat available schedule and propose to MMTH ka.
Then, MMTH will confirm you with agreed date & time.