Following my take on the Work Breakdown structure, the PERT diagram would be different, however the critical path in both versions would flow from Task 1- Task 2 (task 2 is the longest and any delay would compromise the delivery of the project in time. Task 3&4 can be delayed and as long as they are finished within the Task's 2 time frame, they will not hinder the project).