If there is material increase in costs necessarily incurred by the contractor and/or any expected effect on completion and/or delivery schedules resulting directly from any suspension ordered by EGAT, the contractor shall entitled to necessary adjustment to the contract price and/or to the completion or delivery schedules only if and to the extent that it is mutually agreed by EGAT