Step 0 Conform Generator sole plate has been inspected.
Step 1 Preparation work set up gantry track, Tele-Gantry, Lift berm.
Step 2 Generator neutral grounding cubicle to be place in Generator foundation pit.
Step 3 Transport Generator to lifting area.
Step 4 Lift up generator over trailer and move trailer to out site.
Step 5 Set up support beam 11 m. to unloading area.
Step 6 Lowering Generator to support beam.
Step 7 Install Housing closure DE & NDE
Step 8 Lift up Generator over gentry track.
Step 9 Remove support beam 11 m.
Step 10 Set up support block and gentry track 6 m.
Step 11 Move Tele-Gantry with Generator to Gas Turbine foundation.
Step 12 Lowering Generator and Resting on temporary support.
Step 13 Reset Tele-Gantry, gantry track and lifting beam.
Step 14 Set up ringing gear and lift up Generator.
Step 15 Move Tele-Gantry and Generator to foundation.
Step 16 Reset Tele-Gantry, track and beam for lift up Gas Turbine.
Step 17 Transport Gas Turbine to lifting area.
Step 18 m liftting Gas Turbine over trailer and move trailer to out site.
Step 19 Set up support block and gantry track 6 m.
Step 20 moved Tele-Gantry with Gas Turbine To foundation.
Step 21Lowering Gas Turbine on To foundation.
Step 22 Remove Tele-Gantry, lifting
Finish