“Construction Phase” means Construction activities comprising direct (prefabrication assembly, pre-commissioning up to mechanical completion, and other activity specified in Contract) and indirect (scaffolding, transport at site, maintenance of equipment etc.).
“OHSAS” means Occupational Health Safety Assessment Standard.
“TIS” means Thailand Industrial Standard.
“ISO” means International Organization for Standardization
“EIA” means Environmental Impact Assessment. The EIA report is identify the environmental sensitivities and impacts relevant to the project and environmental impact protection requirement.
“Hazard” means intrinsic property or ability of something (e.g. work materials, equipment, work methods and practices) with potential to cause harm.
“Risk” means compiling result of hazard severity and its likelihood that has potential to cause harm.
“3R Principle” means Waste Management Principle: Reduce, Reuse and Recycle.
“PTA” means Pre Task Analysis.
“PPE” mean Personnel Protective Equipment.
“ERT” means Emergency Response Team.