ENS has confirmed that the delivery schedule of 115KV cabinet and
SCADA will be on Oct 15th, 2015 in the part of Tele-Protection will be on
Oct 31th, 2015. SLC advise ENS to revise delivery schedule of Tele-
Protection for catch up the inter-trip testing date on Oct 25th, 2015
which all of 115KV Project including BG-YSP Project should be test on the
same day, because the permission to douse 115KV system many time
from PEA it’s difficulty.