1) The Contractor may only offset claims if these are uncontested or have been declared legally valid.
2) In the event of differences of opinion on additional or modified services, the Contractor shall not have any right of retention or any other right to refuse performance.
3) The Parties agree that liens or other rights of retention to the work to be performed by the Contractor are excluded.