Dear:K.wanpen
Regarding to you mension as below after verify data of november'57.please see detail as below.
L4 m/c
m/c plan = 200 hrs
Actual work = 131.1 hrs
acheivement = 65.55 %
LX m/c
m/c plan = 200 hrs
Actual work = 129.9 hrs
acheivement = 64.95%
Cutting m/c
m/c plan = 200 hrs
Actual work = 151.2 hrs
acheivement = 75.6%
Screen m/c
m/c plan = 200 hrs
Actual work = 34 hrs
acheivement = 17%
After meeting with team found some cause of problem such as order to support printing and screen process not enough (not full machine capacity)and ribbon stock not available and not on time for support machine plan.another cause of problem i will find out and inform to you again.
Remark:
Printing process capacity = 36,000 pcs/day/machine
screen process capacity = 12,000 pcs/day/machine
Cutting process capacity = 30,000 pcs/day/machine
For you information