- Do all quotations pass through Purchasing process already?
Answer : The first quotation haven’t past of bargaining by purchase department yet, because K’Tam from Purchase dept would like supplier to present the price first klub,and he mention when received CER and PR from us then he can bargaining and at in the purchase process
- Before we will have an agreement … we may need to see some work flow / simulation before make decision again (to see possibility of all process flow & concern points) and pls keep Technical Development team involved krub.
Answer : The workflow of machine we already to clear work flow in during machine design with supplier klub and also we has analysis of DFMEA of machine movement, We may going to more analysis to concern critical part of machine, But for machine simulation concept or animation we cannot design and I afraid to lost time of the project ,Which at the moment we have E-Drawing from supplier was sent, and can present to you straight away
- Then we can go for next step on… Agreement contract / SAT – FAT criteria / Service contract / Emergency case…. (Pls keep purchasing team involve also).
Answer : SAT and FAT criteria of course we must talking about that with supplier for aware and agreement of our require ,which CIP team will contact and also the emergency case can we keep as OCAP work flow in the present yesterday klub?
For the project do I have to present to committees PPD2.0 or not klub?
Data for request, We ready support klub
- Do all quotations pass through Purchasing process already?Answer : The first quotation haven’t past of bargaining by purchase department yet, because K’Tam from Purchase dept would like supplier to present the price first klub,and he mention when received CER and PR from us then he can bargaining and at in the purchase process- Before we will have an agreement … we may need to see some work flow / simulation before make decision again (to see possibility of all process flow & concern points) and pls keep Technical Development team involved krub.Answer : The workflow of machine we already to clear work flow in during machine design with supplier klub and also we has analysis of DFMEA of machine movement, We may going to more analysis to concern critical part of machine, But for machine simulation concept or animation we cannot design and I afraid to lost time of the project ,Which at the moment we have E-Drawing from supplier was sent, and can present to you straight away- Then we can go for next step on… Agreement contract / SAT – FAT criteria / Service contract / Emergency case…. (Pls keep purchasing team involve also).Answer : SAT and FAT criteria of course we must talking about that with supplier for aware and agreement of our require ,which CIP team will contact and also the emergency case can we keep as OCAP work flow in the present yesterday klub? For the project do I have to present to committees PPD2.0 or not klub?Data for request, We ready support klub