- Nov 26 , The constructor will install temporary fence on second floor ( Canteen) for joint building and move thing backward from the wall.
- Dec 26,27 Supplier will come to move Server & Telephone Control box to down stair ( QA.room) and setting cable line to temporary office area
So, on that day we can’t use telephone & Internet and now we waiting confirm from UIH , Fujisu supplier ( It’s only plan, may be adjusted and inform you onward )
Sorry for any inconvenience which may cause trouble you.