80 (eighty) percent of the total amount of Engineering and Installation Services shall be
partially made against presentation of invoice (s) after the equipment of each substation/
terminal station/switching station have been successfully installed and passed the Site
Acceptance Test and the one SA at a manned substation, chosen by the Employer, has been
passed the Availability Test