Kaizen shows a lead role for improving the productivity and quality of the products. To meet the target/Productivity from 200 axles per shift (8 hours) to 210 axles per shift, the cycle time should be equal to the Takt Time and hence meeting customer requirement. The company receives the raw material in the form of cast iron beam, then various operations are carried out on this beam like clamping, putting dowel pins, shellac and gasket, fixing and tightening of stud, picking and tightening of anchor plate, placing Z bracket, putting bush and grease filling, placing oil seal, placing hub and brake drum etc to obtain the final product. Table 1 shows detail of station wise operator‘s function and time taken for completion of job at their station. Let T1 and T2 are time taken by the operator in completion of job in two iterations. Mean time is calculated for getting the average time for completing a job at different work stations.