The project was broken down into subprojects, with an integrated plan of more than 17,000 activities. An aggressive schedule was built and interdependencies among activities were clearly defined and all the proper project controls were put into place. A project war room was created and an on-site project location clearly displayed the latest cost and schedule information so that anyone, including the client, could review it. The company held regular public meetings and created a citizens’ advisory board.