Dear Customer
We wish to inform you that our Vado Ligure plant (Italy) will undergo a major Turnaround in August for regulatory requirements and preventive maintenance purpose.
The dates of the closure as follows:
Bulk Sales Orders out of Vado Ligure Plant (IT01)
• Loading Operations will cease on August 19th and be resumed on August 30th, no product movement will be possible in the Aug 20th to 29th window
• Blending units will be down from August 20th till August 29th included
• Reactions units will be down from August 16th till August 30th included
Packaged Goods Sales Order out of Iglom Massa Drumming Site (IT04)
• No limitation for orders placed by the August 1st cut-off date
• Orders placed after the cut-off will have a Plant Preparation Time of 15 Working Days. This special PPT will remain valid for loading dates up to September 9th.
This measure is needed as a consequence of the limited replenishment capacity available from Vado to Iglom
• Supplies out of Botlek (Netherlands) will not be affected
It is extremely important for us that you plan your requested delivery dates taking into considerations the closure dates mentioned above and the relevant loading restrictions.
For deliveries during August we would ask you to plan your orders well in advance so that, if any major impact is noted, we can try to find a solution.
Please feel free to contact your Account Manager , Supply Chain Advisor or me for any clarification.