Total Slack (TS) is a term used by project management professionals. This term describes the additional amount of time that can be lost on a project without delaying the project due date. Conversely, negative slack provides the project manager the amount of time they need to adjust other tasks to make up for the deficit. It is important to know the total slack to assist with incidental delays that might arise. Calculating total slack is not difficult.