Dear Top and Kwan,
We are going to structure the two projects Huay Bong and Watabak a bit differently.
From now on Top will be the project manager for both projects and Kwan will be the site superintendent for both projects. Hugo will support in a technical role and Chertakul will support as a safety advisor. Tads will still act as the site admin representative and will be guided by Yanee who will stay at PTT. Ampa please update the organisation charts accordingly and send to me for review prior to distribution.
Top you will now report directly to Shaun and you should be producing a detailed weekly report for his information.
I will still assist over the next couple of months, however before 19 Feb I want to have the following in place.
LOI – Dut, put the pressure on. Call him every 10 minutes.
Formwork – Hugo is now ordering and will be ordered by early next week.
Shaun has somehow handed back the responsibility for concrete supply to Demco. Dut you need to keep the pressure on for this also with Demco. Michael please update us on the status and plan for finalising the mix design.
Top – we need to get finalised drawings from Demco, but in the meantime see if you can concluded the excavation depth and backfill requirements to ensure that we do not need to go back to footings.
If you are not aware I have resigned effective Songkhran. It has been a pleasure working with