Please focus on CapEx management process as I coached and make procedure for next year. This year I improved CapEx system. Next year please make on IRR/Payback and RAM score to be better than this year. You will have to control all projects that approved from board to be MOC and report CapEx update to K.Thitiphen.
2. MOC in the future that you will take care if higher than 50 K euro up.
3. I liked Khun Phichai’s idea about MOC assignment with queuing such as first MOC to Bancha,Second to Monton third to Thanongsak ,Forth to Treephob then fifth to Bancha again.
4. Plan to assign K.Vinai and K.Wandee to do more on MOC. (Khun Wandee did very good on draftman and GRN jobs)
5. Your role and responsibility on MOC management
6. Review MOC procedure to not be obstruct for practice. Too much signature
7. Grouping MOCs to be 1 MOC because One MOC for one smoke detector. Very terrible
8. Update engineering database because our drawings ,TDS ,manual are not updated.
9. Umbrella contract by UHDE
10. Plan to coordinate and make agreement with M&R team to do MOC if low value. It waste time and more expensive for our team to do.
11. Support K.Monton because he will support you a lot in this year.
12. Assign K.Duen to take care for GRN in IVARA because Khun Wandee is working on this.
13. Be care full on many MOCs that issue in Dec.