Dear Mr Qi
Thank you for update information regarding the raw mill gas flow optimization project of Hon Chong plant, Holcim Vietnam. I will work with Mr Teerasak to finalize the schedule, firstly for Mechanical Engineer. As I sent the operation log sheet data for baseline 350 tph, please also check and let me know your advice.
Dear Mr Teerasak
Regarding the visit schedule of Mechanical engineer from your team, as now Hon Chong is been executing kiln annual shutdown so he may visit on next week. For fix schedule, please send me:
+ Preparation tasks: document, fabricated part by plant, others as required from your side
+ Tasks to be done during the visit and any requirement during the visit and work
Please let me know soon then I will confirm the schedule for your preparation.
Hope to see your team soon and create the result from this project