Dear Khun Kwanravee and Khun Pongsatorn,
Further to the email below please find attached an updated BoQ (Rev 2 dated 31.05.16) for the Crazy Factory project which excludes Phase II and has been prepared based on the drawings issued under cover of the email below. Concerning the attached we advise the following:
· The structural works BoQ section has been amended based on the updated drawings – these will be “For Construction” drawings.
· The architectural works BoQ section has been amended based on the updated drawings – these will be “For Construction” drawings.
· The boundary fence has been added to the Section E.2 of the MEP Infrastructure and External Works section of the BoQ, the balance of the External Works will be updated with the next issue of the BoQ.
· The Provisional Sum section of the BoQ has been amended in the attached.
· All changes from the previously issued GES Tender BoQ Rev 1 have been highlighted for your ease of reference.
A further update (Rev 3) will be issued on 10.06.16 to update the BoQ for the balance of the External Works and the MEP works.
If you have any questions concerning the above and attached please do not hesitate to contact us.