1> Since most of the work in the injection area is completed, I would expect to see everything in its final location.
a. In the injection area we have many boxes kept on the gangway. We need to move these to the right location quickly.
b. Some items like a rack for tools seem to be out of place. I assume we have a layout which specifies location for everything. We need to ensure we place everything in the designated place.
2> The wall between injection area and warehouse has been moved. I am not sure if the work is completed. If yes, then I I have concerns about the quality of work.
3> I see a big opening in this wall. Do we have a plan to have a curtain here? Without a curtain we will have dust entering the injection area.
4> There is lot of dust on the floor in the warehouse. Even during the construction period we need to ensure the best possible dust control in our plant. I expect to see quick improvement here.
5> Regarding the high racks in warehouse. The gangway is too narrow for the stacker operation. I see a high likelyhood of the stacker hitting the wall of the non-prod store or the racks on the other side. We need to review the gangway width. I belive we will need to increase the gangway by approx 250mm.