Note that at 20% of work done (Area Done), more than 70% of all spools have been delivered to the site. According to Howell and Ballard's rule of thumb, this is a favorable indicator for project success. As will be shown later, it is no guarantee for project success, however, particularly when out-of-sequence work leads to mismatches.