6.2.4 When the project is completed, within 10 days after the second party submits the application for project check and acceptance, the project payment which has been made by the first party to the second party should reach 95% of the total contract price;
6.2.5 If the project check and acceptance is qualified, within 30 days after the two parties finish the project settlement, the second party should supply guarantee for defects liability period to the first party which is 5% of the total contract price, and meanwhile, the first party should finish making all the project payment