Dear all,
As your knew, Huawei services contract shall be started from 1-Mar.-16 onward, then until today we could not placing any order for this project because the WBS is not issue yet.
Some services i.e. external messenger, Drinking water, stationary and equipment, and/or etc., need some time to placing order.
We have only 6-business days to go before the contract start, could you please force someone to issue WBS number into SAP system that would be highly appreciated.
Any advice, please