Hou Rui help me check the contractor2 and IKEA about the period time. The both cannot be get finish in the time that we need. They need at least one month and a half because have the long holiday, 1 week, in the first of October.
Today, Kenny took a samples of the entrance wall, it looks very good, but about the price Kenny said we can reduce in two solution
1. Kenny will return to reduce prices by the discount rate, for special, without change the design. But because of the high prices are the price of labor production. Material changes have not helped reduce much.
2. I have to re-design by reducing the number of puzzle [Kenny said I should be decrease the pieces to haft of total to get the price as we want]. I will try and send a new layout to Kenny for checking price again.
And we talk about the kitchen area. Kenny offered that if he contractor all of work, the entrance wall, map wall, poster image on wood plate and kitchen. The overall price is better. And he can be finished by the time because he works in a long holiday.
The wall paint company will come the next week and if the color approve they need two days to get it done.
And now I’m working on a layout of map wall maybe I can send it to you in the evening. Next I just re-design the entrance wall and send to Kenny to get balance the price.