As per Riam discussion with K.Sinchai & Production staff. the boiler ( Hot Air) runs 24 hour so we was starting rice bran production at Rice mill on 28th Jan 16.
it will take 11 days ( exclude sterilization ) and will be complete approximately on 7th Feb.16
.
Can you please ask her to discuss with Noodles Plant to get dates for Hot Air Sterilization and send mail to me?