Can you organize between yourself and Sontaya so that someone will be available to witness the cable installation as per the above schedule in Thakhek. This is an aggressive schedule but it is signed by EdL management so we need to make sure Enova completes as per schedule, or else EdL can potentially claim that PDSR cannot complete the work that is given to them. The schedule starts this Saturday. I may be able to travel to site next week. BCU installation is scheduled to start Jan 18th, so maybe whoever you planned to supervise that can go to THK two days early.
Any deviations from the attached plan or any issues on site please inform us of them immediately – this is our opportunity to speed up Pole and Cable work (at least for Thakhek) – let’s do everything we can to ensure we take advantage of it.