Your statement contradicts as it stands below. The minute clearly identifies that the related documentation will be submitted individually, and the compilation of dossier will take place after full approval is obtained.
We have repeatedly advised that it is not possible to comply to such requirement at this stage, particularly when the said documents have been with GE for more than a month before PIM. Moreover, some of the documents are already at Rev. 2 with BIH comments incorporated.
Having discussed with both our management and VIPCO, I’m afraid our position remains as per the PIM minutes and we would strongly urge GE to take the necessary actions noting that fabrication activities is underway unless GE wants us to put this on HOLD.