As stated on the above response to this RFI, whilst we acknowledge that this is now required and has been requested as outlined on the response to this RFI by both respective parties concerned, we now request the issuance of the appropriate formal site instruction, clearly instructing us to proceed with the provision of the additional ACP cladding at the 9th floor area.