The Contractor shall not subcontract the whole of the Works.
The Contractor shall be responsible for the acts or defaults of any Subcontractor, his
agents or employees, as if they were the acts or defaults of the Contractor. Unless
otherwise stated in the Particular Conditions:
(a) the Contractor shall not be required to obtain consent to suppliers solely of
Materials, or to a subcontract for which the Subcontractor is named in the
Contract;
(b) the prior consent of the Engineer shall be obtained to other proposed
Subcontractors;
(c) the Contractor shall give the Engineer not less than 28 days’ notice of the
intended date of the commencement of each Subcontractor’s work, and of the
commencement of such work on the Site; and