Dear khun Chaiwat, khun Ong-art,
Refer to meeting on 11 Feb 2015 in Lawi’s Bkk office with Mr.Langer, khun Chaiwat and khun Kajohnkiat, Please find attached Revised offer for GGH 9.5 MW Multi Fuel Fired Power plant project - 1st lot.( QU14-229-A02 dated 14-02-2015)
What different from the previous one (QU14-229-A01 dated 29-01-2015)are:
1. Concept for the ventilation roof and 5m. wall around the warehouse. The details will be as discussed in the meeting which I will submit proposal drawing a bit later.
2. Add in concrete slab cost for the area of fuel tower, Combustion chamber, Boiler and ESP = 700 m2
3. Final offer amount after discount as negotiation (49,500,000 THB exclude VAT).
We are pleasure that you are giving us the opportunity to work together in this important project. We hope to hear good news from you very soon.