Which of the following statements best describes the effect of project structure on overall project risk?
A) Highly structured projects are more complex, and run a higher risk of programmers and users misunderstanding the ultimate goals.
B) Projects with relatively undefined goals are more likely to be subjected to users changing requirements and run a higher risk of not satisfying project goals.
C) Highly structured projects tend to be larger, affecting more organizational units, and run both the risk of out-of-control costs and becoming too difficult to control.
D) Less structured projects are more able to be quickly developed, tested, and implemented using cutting-edge RAD and JAD development techniques, and pose less risk of running up unforeseen costs.