• Project duration can be reduced by assigning more resources to
project activities.
• Doing this however increases project cost.
• Decision is based on analysis of trade-off between time and cost.
• Project crashing is a method for shortening project duration by
reducing one or more critical activities to a time less than normal
activity time.
• Crashing achieved by devoting more resources to crashed activities.