With regarding to your below, we would like to inform that as to your request, there might be some shipment that to be too early to make the custom document because many shipment were late schedule of loading plan till late November or even Early December’ 2013.
The details are :
Shipment # 46 : Load 11/11/2013 (Loading by New cartons packing) for delivery testing. (693 cartons)
Shipment # 47 : Load 14/11/2013
Shipment # 48 : Load 18/11/2013
Shipment # 49 : Load 21/11/2013
Shipment # 50 : Load 30/11/2013
Therefore, as advising earlier and in order to make it more realistic close in shipment qty from the production output so that it will not make any problem for your process of custom preparing at your side. We should arrange as suggest earlier to proceed the custom paper for you 2 weeks ahead of actual loading schedule.
In this case, this week, we should prepare for the shipment # 46 and within next Wednesday, we will prepare the customer paper for shipment # 47. For shipment no # 48 will be prepare to you by Nov 4, 2013.
Please kindly note and confirm by return.
Best Regards / Pinthip