The completion percentage of Balance of Plant through 15th October is 29.06%. This is 29.16% behind the schedule. The primary work item behind the schedule is Road works and casting WTG foundation, 115KV substation, 22KV collection system.
Gunkul and relevant subcontractors involved have discussed schedule and recovery measures, and detailed construction schedule with recovery plan was submitted to Powerchaina on 28th June.