Referring to the quality index table (Table 16.5), for n = 10, a Q value of 0.96 indicates a PWL of
83%, which is less than 90%. Hence, the contractor cannot expect to get paid 100% of the pay for
the lot being tested.
Note that when two-sided specifications are used, the PWL is calculated as follows: