Remaining Track material to be handed over to SRT
Dear Sir,
PAC writes to confirm the status of handover of track materials to SRT, currently the handover is ongoing and the completion date is still undetermined.
PAC can confirm that the any outstanding materials not handed over to SRT before the Final Certificate of Payment is issued shall be determined and consequently deducted from the Final Payment to ITD after the Defect Liability Period is concluded as stated in the Conditions of Contract.
PAC is currently inspecting and checking the material with SRT/ITD and upon completion of this task shall inform SRT of the final quantities returned to SRT.